Weeks 11 and 12

Finished concrete foundations - East end of house and Pod.

Clive and Keith dug and installed soak aways. Crusher Keith moved in "on site" and lived in his Land Rover.

Prepared site for hibernation until steels are ready - hopefully by the beginning of December 2017. 

 